Construction of the South-West sewer collector
Concern’s Project Sites

Construction of the South-West sewer collector

Construction period: 11.1990 – 12.2013.

Works on collector construction have commenced in 1990 and stopped in 1996 because of absence of financing. Since 2002, civil works are renewed because of necessity of fulfillment of the "Program of Kyiv City capital construction"

Collector’s length totals  9 818 m

As of beginning of 2009 it is constructed – 5 155 m.
Construction method: shield driving by a PS - 3, 23 mechanized drive-in complex. Along the whole section of mechanized shield driving the collector is coated with reinforced concrete tubings. Internal diameter of collector tunnel is 2,6 m.

The collector is laid on a depth from 56 to 80 m.

 
 
 
Detailed contact information
Question to the expert
Site map

© «Concern «KyivPidzemShlyakhBud», 2009
Site is created by ADV-DVA Company in 2009
Support and Promotion by WebPromotion
«Concern «KyivPidzemShlyakhBud»
Tel.:+380 (44) 253-00-02
tel: +380 (44) 253-00-31
office@kpsb.com.ua